On Thursday and Friday of last week some curb and gutter work was done at the entrances along N Lombard and the driveway to the east of the project, as you can see from the photos.
This week, it is anticipated that a color band between the asphalt and pavers will be installed, they will install the base for the pavers, and the bases for the lighting will be set. Additionally, we should see some work additional work on the seat wall close to E Main Street.
A note about parking: Beginning September 27th, the on-street parking along the front of the project area will be closed while they install pavers to the curb.